The Barbican

Overview

The Barbican is Europe’s largest multi-arts and conference venue, presenting a diverse range of art, music, theatre, dance, film and creative learning events, it is also the home of the London Symphony Orchestra.

The Problem

With such a packed schedule of events, making infrastructure improvements at the Barbican can be a logistical challenge. Typical of most large sites, the Barbican has a number of individual electrical supplies, more than 25 in total. These are spread across the centre.

Our Solution

Following a survey of the site by an electrical engineer and with the help of the Barbican team we identified a suitable area in which to trial the technology. Six supplies entered the building near to the library, a small portion of which was reallocated to house the six VPO® units required.

As with all powerPerfector installations, to minimise disruption, all site works were completed prior to the shutdown. This includes cabling, trunking and any changes needed to the existing switchgear.

The six units were then delivered to site and energised in three tranches over a ten-day period. This allowed the installation team to systematically ensure that all electrical equipment on site was functioning effectively at an optimised voltage.

The Results

Three months after installation, EEVS Insight began to calculate the savings. Using the International Performance Measurement and Verification Protocol (IPMVP) the savings for the project as a whole were calculated to be 7.45%. This represents an annual saving of £23,404.

The saving was just under that guaranteed by powerPerfector of 7.49%. Further investigation revealed that since the tender was submitted, a lighting refurbishments had taken place which impacted on the savings.

The Savings

  • 7.45% kWh Saved
  • 152,800 CO2kg Saved
  • £23,400 Saved

“We were impressed with the professionalism of the powerPerfector installation team, which meant the installations were completed without incident. It was one of the easiest energy efficiency installations we have completed to date.”

“The savings the units have achieved make this an attractive energy efficiency measure. We are working with powerPerfector to identify other opportunities across the Barbican estate.”

Richard O’Callaghan, Project Manager

Download Case Study

Related Case Studies

  • Celtic Manor

    Celtic Manor Resort

    Few sporting events capture the imagination in the same way as the Ryder Cup – steeped in history and loved by golfers on both sides of the Atlantic.

    See The Case Study
  • Marston's White

    Marston's Inns & Taverns

    Marston’s is the leading independent brewing and pub retailing business in the UK.

    See The Case Study
  • QHotels White

    QHotels

    QHotels is a chain of 21 unique four-star hotels, each with its own individual character.

    See The Case Study
  • Westminster Abbey

    Westminster Abbey has been the coronation church since the Battle of Hastings, is the final resting place of 17 monarchs and has played host to 16 royal weddings.

    See The Case Study